In your area

Construction for EGL2 has now begun, with the project expected to be operational in 2029.

You can find out more about the infrastructure in England by looking at our interactive map.

Timeline graphic

Community updates

In order to construct EGL2, we need to conduct a range of activities, such as intrusive surveys, construction of access roads, and out of hours works. On occasion, we will need to put in place traffic management measures, including road closures and traffic light systems, to ensure the safety of all road users and our workforce.

Details of our ongoing and upcoming traffic management measures and other project updates can be found in the tables below:
 

Scottish onshore activities

Works

Location

Measures in place

Expected timings

Link to more information

 

Geophysical surveys 

Sandford Bay and surrounds 

No traffic impact 

Monday 3 - Friday 14 February 2025 

Project update

Water connection works 

Adjacent to A90, Peterhead 

Southbound lane closure 

Monday 13 - Tuesday 21 

January 2025 

Project update

Water and sewage connections 

A90 

2-hour traffic management 

Monday 12 - Friday 23 August 2024 

 N/A

Ducts installation 

U66 

C64B 

Road closure 

U66: Thursday 13 – 30 June 2024 

 

C64B: Saturday 13 – Sunday 15 June 2024 

 N/A

132 kV cable undergrounding 

 

U66 

Road closure 

Sunday 17 – Wednesday 27 March 2024 

 

Monday 18 – Friday 29 March 2024 

 N/A

11 kV cable undergrounding and rerouting

A90

U66

Traffic management

Wednesday 21 February - Wednesday 28 February 2024

N/A



English onshore activities

Works

Location

Measures in place

Expected timings

Link to more information

 

Ground surveys

B1249, Skerne and Wansford, East Riding

Two-way traffic management system with temporary traffic lights

Friday 14 – Tuesday 18 February 2025

Traffic management map

Geophysical surveys

Fraisthorpe Sands

No impact to public access

Monday 10 – Friday 14 February 2025

N/A

Ground surveys

Main Street, Little Kelk, Great Kelk, East Riding

Three-way stop and go traffic management system

Thursday 6 - Monday 10 February 2025

N/A

Ground surveys

Gransmoor Lane, Great Kelk, East Riding

Stop and go traffic management system

Wednesday 5 – Monday 10 February 2025

N/A

Ground surveys

Gransmoor Lane, Great Kelk, East Riding

Stop and go traffic management system

Tuesday 4 - Wednesday 5 February 2025

N/A

Ground surveys

Redhouse Lane, Long Drax, Drax, North Yorkshire,

Two-way traffic management system with temporary traffic lights

Tuesday 28 – Thursday 30 January 2025

Traffic management map

Ground surveys

Hull Road, Newsholme, East Riding

Two-way traffic management system with temporary traffic lights

Monday 27 - Wednesday 29 January 2025

Traffic management map

Ground surveys

B1228, Howden, East Riding

Two-way traffic management system with temporary traffic lights

Thursday 23 – Monday 27 January 2025

Traffic management map

Ground surveys

A614, Spaldington, East Riding

Two-way traffic management system with temporary traffic lights

Wednesday 22 - Friday 24 January 2025

 

Traffic management map

Ground surveys

Wood Lane, Howden, East Riding

Two-way traffic management system with temporary traffic lights

Tuesday 21 – Thursday 23 January 2025

Traffic management map

Ground surveys

A614, Spaldington, East Riding

Two-way traffic management system with temporary traffic lights

Tuesday 21 – Thursday 23 January 2025

 

Traffic management map

Ground surveys

Cliffe Road, Market Weighton, East Riding

Three-way traffic management system with temporary traffic lights

Monday 20 - Thursday 23 January 2025

Traffic management map

Ground surveys

Skiff Lane, Holme upon Spalding Moor, East Riding

Stop and go traffic management system

Monday 13 – Wednesday 15 January 2025

N/A

Ground surveys

Sand Lane, North Cliffe, south of Market Weighton, East Riding

Three-way stop and go traffic management system

Monday 13 – Friday 15 January 2025

N/A

Ground surveys

Beverley Road, Hutton Cranswick

Two-way traffic management system with temporary traffic lights

Wednesday 15 – Friday 17 January 2025

 

Traffic management map

Ground surveys

Arras Hill, Market Weighton

Two-way traffic management system with temporary traffic lights and lane closures

 

Thursday 16 – Monday 20 January 2025

Traffic management map

Early survey works for the installation of a construction compound

Sancton Road (A1034), Market Weighton

Two-way traffic management system with temporary traffic lights

Tuesday 26 – Saturday 30 November 2024

Traffic management map

Wren Hall Converter Station site access

Wren Hall Lane, Drax

Road closure

Tuesday 22 October – Monday 11 November 2024

Traffic management map

Wren Hall Converter Station site access

New Road, Drax

Three-way traffic management system with temporary traffic lights

Monday 9 September – Sunday 13 October 2024

Traffic management map


What we are constructing in your area
 

    Construction of the Peterhead Converter Station began in October 2024.

    This was preceded by a period of enabling works to prepare the site. These works, carried out by our contractor, Keltbray, which included moving and replacing some existing electrical infrastructure on the site to make way for the converter station platform, as well as creating access roads and new junctions, water and sewerage connections, and creating the car park and site offices for our contractors.

    Working hours

    The site will operate a 5-6 day working week, with operations and deliveries being undertaken between 7am-7pm on weekdays and 7am-1pm on Saturdays. Please note, there will be very limited work on Saturdays initially.

    Any night-time operations will need to be approved by Aberdeenshire Council prior to the works starting.


     

    Our contractor, Prysmian, will lay the subsea cable using their state-of-the-art Cable Installation Vessels, making use of various techniques to accurately lay the cable on the seabed and bury it.

    Monna Lisa

    When the cable is laid on the seabed it is also buried using a plough. In areas where the use of the plough is not applicable, a trenching tool may be used, or alternatively the cable may be buried using rock placement techniques to ensure sufficient protection.

    Once both the onshore and offshore cables are laid and buried, they are joined together at both landfall locations. To minimise construction impacts at the landfalls, the cables will be installed using horizontal directional drilling (HDD). This method installs ducts, which are tubes used to carry cables underneath the nearshore area and out to sea, to reduce the impact on protected or rocky coastlines.

     

    The onshore construction process involves several key stages.

    First, trenches will be excavated to the required depth for the cable. If we need to cross existing infrastructure like roads or utilities, we use horizontal directional drilling (HDD) to minimise disruption.

    Next, pipes or ducts are installed in the trenches and HDD tunnels. After that, the trenches are backfilled with soil or other materials. Finally, the HVDC cables are pulled through the installed pipes or ducts, completing the process.

    As part of the construction process, we will also be constructing a temporary haul road that will run parallel to the route. This is a temporary road that will service the installation of cables along the cable route. It will also enable the delivery of resources and personnel throughout the build. Once completed, the land will be returned to its pre-construction state. 

    This access road will include the construction of various bellmouths. These are access points across the route that will allow for the safe entrance and exit of vehicles to the site and will also help to service our three construction compounds that are being erected at strategic points along the onshore cable route.

    These compounds are temporary and will be removed and the land reinstated following completion of the cable route. 

     

    Construction for the Wren Hall Converter Station began in September 2024, in order to set up the construction compound. This includes establishing a site office, a welfare area, canteen, car park and various construction storage areas.

    From November 2024 to Spring 2025, we will be conducting bulk earthworks, to stabilise the ground and enable the construction of the converter station platform.

    Working hours

    The site will operate a 5-6 day working week, with operations and deliveries being undertaking between 7am-7pm on weekdays and 8am-5pm on Saturdays.

    There may be some occasions where work is required outside of these hours, for example, the delivery of abnormal loads or particular construction activities such as the pouring of concrete.